Kaika V5 real-app alignment pass โ this build is being brought section-by-section into line with the approved review HTML while preserving real operational structure and live data pathways.
Production Stages
Operational stage control across readiness, blockers, owners, and next actions.
Thursday, April 23, 2026Fiji Time (GMT+12)
Unknown user
Role not set
Kaika Operating Workflow
1. Booking / Slot ReservationCommercial gate
2. Design / Scope ConfirmationPre-build setup
3. Materials Procurement & ReadinessCritical control stage
4. Hull / Structural BuildWorkshop execution
5. Fit-Out / OutfittingOperational build phase
6. Systems / Mechanical / Electrical InstallTechnical integration
7. Finishing / QA / Sea TrialClose-out control
8. Delivery / HandoverFinal milestone
Stage Control Summary
| Build | Current Stage | Blocker | Commercial | Stage / billing gate | Action now | Labour |
|---|---|---|---|---|---|---|
| Geoff Doig 28ft Catamaran Rebuild | Delivery / Handover | Final payment remains unpaid before close-out | Overdue ยท $33,425.73 outstanding | Blocked by unpaid milestone | Finance follow-up required | Close-out coordination |
| Greenhouse Bay 25ft Cabin Boat | Fit-out / Fitting | Residual balance should be cleared during close-out | Residual outstanding ยท $777.92 outstanding | Paid to current stage | Warn only | Close-out coordination |
| Guy Shahar 28ft Split Console | Fit-out / Fitting | Flooding recovery and staffing disruption | Milestone 2 outstanding ยท $32,101.45 outstanding | Blocked by unpaid milestone | Cannot advance | 3 workers |
| Mike Tubbs 28ft Center Console | Hull / Structural build | Needs firm material readiness tracking | Current on issued invoices ยท $0.00 outstanding | Paid to current stage | Can continue | 2 workers |
| Sea Fiji 36 Passenger Transfer | Reserved / Planned | Still needs production slot confirmation | Paid ยท $0.00 outstanding | Billing ahead of production | Warn only | 3 workers planned |
| Swell Ltd 38ft Pilot House Catamaran | Hull / Structural build | Hull / structural execution now underway and needs disciplined production loading | Deposit and engine paid ยท $0.00 outstanding | Paid to current stage | Can continue | Pre-start loading |
Stage Action Detail
| Stage | Owner | Readiness | Blocker | Next action |
|---|---|---|---|---|
| booking | Mike Tubbs 28 Centre Console | 41% | Validated save-readback path (validation-2026-05-13T03:28:29.176Z) | Validation next action validation-2026-05-13T03:28:29.176Z |
| fitout | Guy Shahar 28 Full Cabin | 68% | Flood-delay recovery still affecting handover certainty | Reconfirm fit-out completion sequence and handover dependencies. |
| booking | Mike Tubbs 28 Centre Console | 40% | Material readiness needs to be locked before accelerating production | Confirm material availability and shift into hull build readiness. |
| design | Sea Fiji 36 Passenger Transfer | 18% | Production slot and commitment still not finalised | Confirm slot decision and convert planning status into active schedule. |
Stage Update Controls
Mutation path: Represents the operational mutation path for stage movement, blocker capture, and readiness changes.
Stage Update Draft
Build
KAI-026-GD
Stage key
delivery
Readiness %
92%
Blocker type
schedule
Blocker note
Final payment remains unpaid before close-out
Next action
Advance Geoff Doig 28ft Catamaran Rebuild to the next operational checkpoint when ready.
Stage Update Draft
Build
KAI-025-GB
Stage key
fitout
Readiness %
88%
Blocker type
commercial
Blocker note
Residual balance should be cleared during close-out
Next action
Advance Greenhouse Bay 25ft Cabin Boat to the next operational checkpoint when ready.
Stage Update Draft
Build
KAI-028-GS
Stage key
fitout
Readiness %
68%
Blocker type
commercial
Blocker note
Flooding recovery and staffing disruption
Next action
Advance Guy Shahar 28ft Split Console to the next operational checkpoint when ready.
Stage Update Draft
Build
KAI-028-MT
Stage key
hull
Readiness %
32%
Blocker type
material
Blocker note
Needs firm material readiness tracking
Next action
Advance Mike Tubbs 28ft Center Console to the next operational checkpoint when ready.
Stage Update Draft
Build
KAI-036-SF
Stage key
design
Readiness %
18%
Blocker type
commercial
Blocker note
Still needs production slot confirmation
Next action
Advance Sea Fiji 36 Passenger Transfer to the next operational checkpoint when ready.
Stage Update Draft
Build
KAI-038-SW
Stage key
hull
Readiness %
46%
Blocker type
commercial
Blocker note
Hull / structural execution now underway and needs disciplined production loading
Next action
Advance Swell Ltd 38ft Pilot House Catamaran to the next operational checkpoint when ready.